Tomorrow (2018-08-08), starting at 13:00 UTC, we will add a linecard to pdx1-hil1-vac1-a75, to prepare for additional capacity.
During this operation, which should last 30 minutes, this VAC will be isolated, and traffic will flow through the other VACs. No impact is expected.
Date: Wednesday, 08 August 2018, 15:22PMDuring this operation, which should last 30 minutes, this VAC will be isolated, and traffic will flow through the other VACs. No impact is expected.
Reason for closing: Done
We are now isolating pdx1-hil1-vac1-a75 to start this operation
The linecard has been inserted, the ports are being configured
The linecard is configured, we are doing some tests before putting the a75 back in production
We are now putting pdx1-hil1-vac1-a75 back in production